Report expires:   30/01/2025  

Report of thorough examination of lifting equipment

This report complies with the requirements of the Lifting Operations and Lifting Equipment Regulations 1998


    Last Updated       Date of report         Report number    
Jul 30, 2024 Jul 30, 2024 dcv-2682-genie-z30-s-n-z30nd-821

Client details

   Name and address of employer           Address of the premesis      
DCV engineering Ltd Rixon road Wellingborough NN84BB Malpassfarm suez rugby CV21 1QJ

Equipment / Examination

Description of the equipment Safe working load Date of exam Date of manufacture Date of last examination
DCV 2682 Genie Z30 s/n Z30ND-821 Max 227 kg Jul 30, 2024 2019 02-01-2024
Defects
None

Is this the first examination after installation? Has the equipment been installed correctly?
no yes

Was the examination carried out? In accordance of the examination scheme? In exceptional circumstances?
In an interval of 6 months yes no

Identification of any part found to have a defect which is or could become a danger to persons and a description of this defect:

No defects


Particulars of any test carried out as part of the examination?

Full test carried out


Is the above a defect which is immediate danger to persons no
Is the above a defect which is not yet but could become an immediate danger to persons no
Is this equipment safe to operate? Yes

Name of person authenticating this report: Andrew Sands
The Loler Man - NN15 6TP